Question 1
All of the following are important outputs of project scheduling, except:
a) Identification of slack times for all activities and paths
b) Earliest and latest time each activity can be completed
c) Networks and paths
d) Identification of critical activities
Question 2
Which of the following project categories might lead to the other project categories?
a) Derivative projects
b) Breakthrough projects
c) Platform projects
d) R&D projects
Question 3
Duration of critical path – path duration = __________?
a) Latest finish time
b) Critical time
c) Path slack
d) Latest start time