(Solved) : Two Different Manufacturing Processes A And B Can Be Used . . .

Two different manufacturing processes, A and B, can be used to produce a certain component. The specification on the dimension of interest is 100.00 mm ( 0.20 mm. The output of process A follows the normal distribution, with ( = 100.00 mm and ( = 0.10 mm. The output of process B is a uniform distribution defined by f(x) = 2.0 for 99.75 ( x ( 100.25 mm. Production costs per piece for processes A and B are each $5.00. Inspection and sortation cost is $0.50 per piece. If a part is found to be defective, it must be scrapped at a cost = twice its production cost. The Taguchi loss function for this component is given by L(x) = 2500(x – N)2 , where x = value of the dimension and N is its nominal value. Determine the average cost per piece for the two processes.

Expert Answer

Attached

Posted in Uncategorized